Tuesday, 14 June 2011

The finishing line is in sight

In May the latest site was handed over and people started moving into Bewerley Court. Although the site is relatively small the buildings are impressive with tenanted flats, transitional housing and respite accommodation all available.

The very final phase of building will be completed this month when Cottingley Court is handed over on the 20th June.

LiLAC will then have completed 15 phases over a 3 year period with all the buildings being ready within days of the planned dates.